In Part 5 we mapped the slab, ground the high spots, filled the low ones and checked it for moisture. The floor is flat. Now the new tile goes down.
In this series we install the floor before the cabinets. The tile runs wall to wall, under the base cabinets, the dishwasher and the refrigerator. If the layout ever changes, there is no hole in the floor, and the dishwasher and fridge sit at the same height as the finished floor in front of them. It costs a few more boxes of tile, and it saves a lot of trouble later.
Setting a tile floor well is not about speed. It is about three things: a layout that puts the cuts where nobody looks, enough mortar under every tile, and tiles that sit flat against their neighbors. Here is how we do each one.
Step 1: Dry layout before any mortar is mixed
Before a single bag of mortar is opened, we lay out the floor on paper and on the slab.
- Find the focal lines. The first lines we look at are the ones people see: the line across the entry to the kitchen, the line along the island and the front of the base cabinets. A full tile at the entry looks right. A two-inch sliver at the entry looks like a mistake.
- Center the room or the island. In most kitchens we center the layout on the island or on the main walkway, so the cuts on both sides are the same size.
- Check the cut sizes at every wall. We do the math for each wall. If a layout leaves a cut smaller than about a third of a tile, we shift the whole grid. A narrow cut against a wall is hard to set, easy to crack and the first thing the eye catches.
- Plan the transitions. Where the kitchen meets the family room, a hallway or a different floor, the joint has to land in a straight line under a door or along a wall, not in the middle of an opening.
Then we lay a few rows of tile dry, with spacers, along the main lines. Seeing the real tiles on the real slab catches problems that a drawing misses, such as a wall that runs out of square and makes the last row taper.
Step 2: Snap the control lines
With the layout decided, we snap chalk lines on the slab: one main line along the length of the room and one at a perfect 90 degrees to it. We check the square with the 3-4-5 method, the same one we used to check the corners in Part 1: 3 feet on one line, 4 feet on the other, and the diagonal must read exactly 5 feet. On a big floor we use 6-8-10 for more accuracy.
Every tile in the room is set from those lines. If the lines are right, the grid stays straight from the entry to the far wall.
Step 3: Choose and mix the mortar
The mortar under a tile is what holds it. For the large-format porcelain most South Florida homeowners choose today (24 by 24 inches, 12 by 24, or plank tile up to 48 inches), we use a polymer-modified mortar rated for large and heavy tile. It holds a thicker bed without the tile sinking as it cures.
- Mix to the manufacturer’s water ratio. Too much water makes mortar easy to spread and weak once it cures.
- Let it slake. After the first mix, the mortar rests for a few minutes and is mixed again. That lets the polymers activate.
- Mix only what can be used. Mortar has an open time, the window in which a tile will still bond to it. In a hot, humid South Florida garage or a kitchen with the AC off, that window is shorter. We mix in batches the crew can set in about half an hour.
Step 4: The right trowel and the right technique
- Trowel size follows tile size. For tile 15 inches and up, we usually start with a 1/2 inch square notch trowel. The goal is not the trowel, it is the coverage.
- Key in, then comb. The flat side of the trowel presses a thin layer of mortar into the slab. Then the notched side combs ridges in one direction.
- Comb in straight lines, not swirls. Ridges in one direction let air escape when the tile is pressed down. Swirls trap air pockets.
- Back-butter every large tile. We spread a thin, flat coat of mortar on the back of each large tile. This fills the small hollows on the back and is the single biggest step toward full coverage.
Step 5: Set, slide and check coverage
Each tile is placed slightly off its final position and slid about a quarter inch across the ridges, perpendicular to them, to collapse the ridges and spread the mortar. Then it is pressed into place.
The only way to know a tile has full contact is to look. Every so often, especially at the start, we lift a freshly set tile and check the back. For floors, the target is at least 80 percent coverage, and for large-format tile and wet areas we aim for 95 percent, with mortar under all the corners and edges. Empty corners are where tiles crack when a heavy pot or a chair leg lands on them.
Step 6: Leveling clips and lippage
Lippage is the height difference between the edges of two neighboring tiles. You feel it with bare feet and see it when light comes in low across the floor. Large tiles are more prone to it because they are rarely perfectly flat from the factory.
- Leveling clips. We use a tile leveling system: clips slide under the edges of neighboring tiles, and a wedge or cap pulls the edges into the same plane while the mortar cures.
- Offset for plank tile. Long plank tiles often have a slight bow in the middle. We keep the offset to one third of the length or less, not the common one half, so the high middle of one tile never lands next to the low end of another.
- Check with a straight edge. As each row goes down, a straight edge across the tiles shows any tile that sits high or low while the mortar is still workable.
Step 7: Cuts, edges and movement joints
- Cuts against walls stay about 1/4 inch away from the wall. The baseboard covers that gap later. Tile that touches the wall has no room to move.
- Movement joints. Tile and concrete move with temperature and humidity. Along the perimeter and at intervals in larger rooms, we leave joints that are later filled with flexible sealant instead of grout. In a long open-plan space, skipping them is how tiles tent up and crack years later.
- Around the island and the cabinet line, the cuts are made clean and square. Anything under a cabinet will not be seen, but it still gets full mortar so it supports the cabinet’s weight.
Step 8: Clean as we go
Mortar that squeezes up into the joints is removed before it hardens, so the grout in Part 7 has full depth. The tile faces are wiped clean. Nobody walks on the floor until the mortar has cured enough, usually 24 hours, and the room is closed off with a sign on the door.
How long it takes
A typical kitchen floor with large-format porcelain takes one to two days to set, depending on the size of the room and the number of cuts. Grout and sealing come next, after the mortar has cured.
Frequently asked questions
How much mortar coverage does tile need?
At least 80 percent on a dry floor, and 95 percent for large-format tile and wet areas, with every corner and edge supported. We check by lifting tiles during the install.
Why back-butter large tiles?
The back of a large tile is never perfectly flat. A thin coat of mortar on the back fills those hollows, which is the most reliable way to get full contact.
What is lippage, and how is it avoided?
It is a height difference between neighboring tile edges. We avoid it with a flat slab, back-buttering, a leveling clip system and a short offset on plank tile.
Should the tile go under the cabinets?
In this series, yes. It keeps the floor continuous, keeps the dishwasher and fridge openings at the right height, and makes future changes easier.
When can you walk on new tile?
Usually after about 24 hours, once the mortar has cured enough. Heavy traffic and cabinet installation wait until after grout.
What comes next
The tile is down and cured. In Part 7 we grout the floor, clean off the haze, seal it if the grout needs it and protect it so the cabinet installation can start.