
The floor from Part 7 is grouted, cured and covered. Today the kitchen starts to look like a kitchen: the base cabinets go in.
Of everything in a kitchen, base cabinets have the least room for error. They carry a stone countertop that can weigh well over a thousand pounds, a sink full of water and a dishwasher that has to slide into an exact opening. If the bases are not level, the countertop rocks, the drawers drift open and the dishwasher door rubs. If they are not straight, the stone has a gap at the wall. Everything that comes after sits on what we do today.
Step 1: Check the delivery before installing anything
Cabinet boxes are unwrapped and checked against the order and the layout, one by one: size, door style, finish, hinge side, drawer count. Each box is checked for shipping damage. A wrong or damaged box found now is a phone call. Found after it is screwed to the wall, it is a delay.
We also confirm the appliance specs one more time: the dishwasher opening, the range width and the refrigerator opening, against the actual models that will be installed.
Step 2: Find the high point and set the level line
Back in Part 5 we set a cabinet reference line. Today we use it.
- Find the high point of the floor along the cabinet run with a laser level. Cabinets always start from the highest point. You can raise a cabinet with shims. You cannot lower it into the floor.
- Mark the top of the base cabinets on the wall, measured up from the high point. Standard base cabinets are 34 1/2 inches tall, and with a countertop of about 1 1/2 inches the work surface lands at the standard 36 inches.
- Run that level line around every wall that gets cabinets, including the island position on the floor. Every box will be set to this line.
- Mark the studs above the line. Every cabinet is screwed into framing or the blocking we installed in Part 4, never only into drywall.
Step 3: Start in the corner
The first cabinet set is almost always the corner cabinet, because the corner controls both runs that leave it. If the corner is set out of level or out of square, the error grows along both walls.
- The corner box is placed, and the top is brought to the level line with shims under the box.
- It is checked for level front to back and side to side, and for plumb on the face.
- Where the wall is not flat, shims go behind the back rail at the stud, so the screw does not pull the box out of square.
- It is screwed through the back rail into the stud or blocking with cabinet screws.
Step 4: Set the run, box by box
Each next cabinet is placed beside the last one, leveled to the line and then joined to its neighbor before it is screwed to the wall.
- Clamp the face frames flush. The two cabinet faces are clamped so the fronts and tops line up exactly.
- Join the boxes. They are joined with cabinet connector screws through the face frames or the sides, in pre-drilled holes so the wood does not split. On frameless cabinets, the sides are joined with connector bolts.
- Then screw to the wall. Only once the box is level and joined to its neighbor does it get screwed to the studs.
- Check the whole run. Every few boxes, a long level across the tops confirms the run is still flat and straight. A small error caught here is easy to fix. A small error over twelve feet is a countertop that does not fit.
Step 5: Shims, toe kicks and the gaps nobody should see
- Shims are trimmed flush and hidden behind the toe kick, never left sticking out.
- On an uneven floor, the toe kick is scribed so it follows the floor while the cabinet above stays level. That way the line at the floor looks right even where the floor is not perfect.
- Fillers go where a cabinet meets a wall or an appliance, so drawers and doors can open without hitting the wall or the refrigerator handle. They are scribed to the wall shape we measured in Part 1.
Step 6: Openings for the appliances
The spaces for the dishwasher and the range are part of the cabinet installation, not an afterthought.
- Dishwasher opening. Usually 24 inches wide, measured and checked for height from the finished floor to the underside of the future countertop. The cabinets on each side are set perfectly parallel, so the dishwasher slides in without rubbing.
- Range opening. Measured to the exact width of the range model, with the countertop edges planned so the range sits flush.
- Sink base. The back panel is cut cleanly around the drain and supply lines from Part 3, with the openings sized for the pipes and nothing more.
Step 7: The island
An island has no wall to hold it. It has to be anchored to the floor.
- Position. The island is placed from the layout lines, checking the walkway on each side. We usually plan for at least 42 inches between the island and the cabinets across from it, more where two people cook at once.
- Anchoring. Wood cleats are fastened to the tile floor and slab with the right anchors for concrete, set inside the island footprint. The island boxes go over the cleats and are screwed to them, so the island cannot slide or tip.
- Utilities. If the island has a sink or outlets, the plumbing and electrical stubs from Part 3 come up exactly inside the box. That is why they were placed from the cabinet drawings and not from the old kitchen.
- Seating side. Panels and supports for the countertop overhang are planned now. We cover overhang support in Part 11.
Step 8: Check before the countertop is measured
Before anyone from the countertop shop comes to measure, Edgar checks the bases:
- Level and flat along every run and across the island.
- Every box joined and screwed to framing.
- Openings for the dishwasher and range at the right width and height.
- Sink base cut and ready, with the sink model confirmed.
- Nothing will move when a 1,000 pound slab is set on it.
Frequently asked questions
Why do cabinets start at the high point of the floor?
Because a cabinet can be raised with shims but cannot be lowered. Starting from the high point keeps every box at the same level line.
What holds base cabinets in place?
Screws through the back rail into studs or blocking, and connector screws between neighboring boxes. Islands are screwed to cleats anchored to the floor.
How long does base cabinet installation take?
For a typical kitchen, one to two days for the base cabinets and island, depending on the number of boxes and how much scribing the walls need.
How much space should there be around an island?
We usually plan at least 42 inches of walkway, and more in kitchens where two people cook at the same time.
What if the floor is not level?
The cabinets are shimmed to a level line, and the toe kick is scribed to follow the floor, so the cabinets are level and the line at the floor still looks clean.
What comes next
The bases are set, level and tight. In Part 9 the upper cabinets go up, along with fillers, end panels, crown molding and the hardware.
Planning a kitchen remodel in Coral Springs or nearby? See our kitchen remodeling page or schedule a site visit with Edgar at stronghandsflpro.com/contact or (754) 261-2153.
