The floor from Part 7 is grouted, cured and covered. Today the kitchen starts to look like a kitchen: the base cabinets go in.

Of everything in a kitchen, base cabinets have the least room for error. They carry a stone countertop that can weigh well over a thousand pounds, a sink full of water and a dishwasher that has to slide into an exact opening. If the bases are not level, the countertop rocks, the drawers drift open and the dishwasher door rubs. If they are not straight, the stone has a gap at the wall. Everything that comes after sits on what we do today.

Step 1: Check the delivery before installing anything

Cabinet boxes are unwrapped and checked against the order and the layout, one by one: size, door style, finish, hinge side, drawer count. Each box is checked for shipping damage. A wrong or damaged box found now is a phone call. Found after it is screwed to the wall, it is a delay.

We also confirm the appliance specs one more time: the dishwasher opening, the range width and the refrigerator opening, against the actual models that will be installed.

Step 2: Find the high point and set the level line

Back in Part 5 we set a cabinet reference line. Today we use it.

Step 3: Start in the corner

The first cabinet set is almost always the corner cabinet, because the corner controls both runs that leave it. If the corner is set out of level or out of square, the error grows along both walls.

  1. The corner box is placed, and the top is brought to the level line with shims under the box.
  2. It is checked for level front to back and side to side, and for plumb on the face.
  3. Where the wall is not flat, shims go behind the back rail at the stud, so the screw does not pull the box out of square.
  4. It is screwed through the back rail into the stud or blocking with cabinet screws.

Step 4: Set the run, box by box

Each next cabinet is placed beside the last one, leveled to the line and then joined to its neighbor before it is screwed to the wall.

Step 5: Shims, toe kicks and the gaps nobody should see

Step 6: Openings for the appliances

The spaces for the dishwasher and the range are part of the cabinet installation, not an afterthought.

Step 7: The island

An island has no wall to hold it. It has to be anchored to the floor.

Step 8: Check before the countertop is measured

Before anyone from the countertop shop comes to measure, Edgar checks the bases:

Frequently asked questions

Why do cabinets start at the high point of the floor?

Because a cabinet can be raised with shims but cannot be lowered. Starting from the high point keeps every box at the same level line.

What holds base cabinets in place?

Screws through the back rail into studs or blocking, and connector screws between neighboring boxes. Islands are screwed to cleats anchored to the floor.

How long does base cabinet installation take?

For a typical kitchen, one to two days for the base cabinets and island, depending on the number of boxes and how much scribing the walls need.

How much space should there be around an island?

We usually plan at least 42 inches of walkway, and more in kitchens where two people cook at the same time.

What if the floor is not level?

The cabinets are shimmed to a level line, and the toe kick is scribed to follow the floor, so the cabinets are level and the line at the floor still looks clean.

What comes next

The bases are set, level and tight. In Part 9 the upper cabinets go up, along with fillers, end panels, crown molding and the hardware.