Remodeled bathroom with double vanity and glass shower

This post opens our bathroom series. Like the kitchen series, we walk through a full bathroom remodel stage by stage, the way we run it in homes across Broward and Palm Beach Counties. Each part covers one stage in detail.

A bathroom is small, but it is the most technical room in the house per square foot. In a few dozen square feet you have water supply, drains, a shower that must stay waterproof for decades, tile on every surface, electrical next to water and an exhaust fan fighting South Florida humidity. Most bathroom problems we are called to fix, such as leaking showers, cracked tile and mold, started with a decision made in a rush at the beginning.

Step 1: Decide what changes and what stays

The first conversation is about layout, because layout decides the scope:

Step 2: Choose the items that set the rough-in

Some selections must be made before demolition, because the plumbing and framing are built around them:

Step 3: Measure the room

We measure the bathroom the way the tile installer and glass company will need it:

Step 4: Order the long-lead items

Custom vanities, special tile, glass enclosures and some plumbing fixtures have lead times. Vanities and tile are ordered before demolition. Shower glass is measured only after tile is finished, which we explain in Part 14.

The order of work

This is the sequence we follow on a full bathroom remodel, and the outline of this series:

  1. Planning, selections and measurements (this part)
  2. Protecting the house and shutting down the bathroom
  3. Demolition down to the studs
  4. Repairing water damage, mold and rot found behind the walls
  5. Plumbing rough-in and the shower valve
  6. Moving a toilet or drain on a concrete slab, when the layout changes
  7. Electrical, lighting and the exhaust fan
  8. Building the shower pan: slope, drain and curb
  9. Waterproofing the shower before tile
  10. The flood test: 24 hours of water before any tile
  11. Wall tile, niches and clean cuts
  12. Floor tile, grout and sealing
  13. Vanity, toilet and fixtures
  14. Shower glass, accessories and the final walkthrough

How long does a bathroom remodel take?

For a typical full bathroom with a tile shower, the work on site usually runs three to five weeks once the vanity and tile are on hand. The waterproofing cure and flood test alone take several days, and that time should never be skipped. Moving plumbing on a slab, repairing damage found behind the walls, and waiting for custom glass can add time.

Frequently asked questions

What should be chosen before a bathroom is demolished?

The shower valve, shower drain type, toilet, vanity and sink, and the location of niches, bench and grab bars. They decide the plumbing and framing.

In what order is a bathroom remodeled?

Demolition, repairs, plumbing and electrical, shower pan and waterproofing, flood test, tile, vanity and fixtures, then glass and the final walkthrough.

How long does a bathroom remodel take?

Usually three to five weeks of work on site for a full bathroom with a tile shower, once materials are on hand.

Can a bathroom be remodeled without moving the plumbing?

Yes, and it is usually faster and less expensive. Keeping the toilet and drains in place is a common way to control the budget.

What comes next

In Part 2 we protect the rest of the house and shut the bathroom down before demolition.