This post opens our bathroom series. Like the kitchen series, we walk through a full bathroom remodel stage by stage, the way we run it in homes across Broward and Palm Beach Counties. Each part covers one stage in detail.
A bathroom is small, but it is the most technical room in the house per square foot. In a few dozen square feet you have water supply, drains, a shower that must stay waterproof for decades, tile on every surface, electrical next to water and an exhaust fan fighting South Florida humidity. Most bathroom problems we are called to fix, such as leaking showers, cracked tile and mold, started with a decision made in a rush at the beginning.
Step 1: Decide what changes and what stays
The first conversation is about layout, because layout decides the scope:
- Does the toilet stay where it is? Moving a toilet on a concrete slab means cutting the floor. It is possible, and we cover it in Part 6, but it changes the cost and the schedule.
- Tub, shower or both? Replacing a tub with a walk-in shower is one of the most requested changes in South Florida. It affects the drain, the floor slope and the waterproofing.
- Curb or curbless shower? A curbless entry needs the floor lowered or built up differently. It has to be planned before demolition.
- Single or double vanity? A second sink needs a second drain and supply.
Step 2: Choose the items that set the rough-in
Some selections must be made before demolition, because the plumbing and framing are built around them:
- Shower valve and trim. The valve goes inside the wall. Its type (pressure balance or thermostatic) and the depth of the wall finish decide how it is installed. We cover this in Part 5.
- Shower head, hand shower and body sprays. Each adds a pipe in the wall.
- Shower drain type. A center drain or a linear drain changes how the shower floor is sloped.
- Toilet. The rough-in distance from the wall to the drain, usually 12 inches, must match the toilet model.
- Vanity and sink. The height of the drain and supplies depends on the vanity and whether the sink is undermount or vessel.
- Niches, bench and grab bar locations. These need framing and blocking before the walls close.
Step 3: Measure the room
We measure the bathroom the way the tile installer and glass company will need it:
- Wall lengths and heights, and whether the walls are plumb. A shower wall that leans shows up as a tapered tile cut in the corner.
- Floor level and slab condition. A laser shows the high and low points.
- Window position. A window inside a shower is common in older South Florida homes. It needs special waterproofing and sill detail.
- Door swing and clearances in front of the toilet and vanity.
- The exhaust fan route to the outside.
Step 4: Order the long-lead items
Custom vanities, special tile, glass enclosures and some plumbing fixtures have lead times. Vanities and tile are ordered before demolition. Shower glass is measured only after tile is finished, which we explain in Part 14.
The order of work
This is the sequence we follow on a full bathroom remodel, and the outline of this series:
- Planning, selections and measurements (this part)
- Protecting the house and shutting down the bathroom
- Demolition down to the studs
- Repairing water damage, mold and rot found behind the walls
- Plumbing rough-in and the shower valve
- Moving a toilet or drain on a concrete slab, when the layout changes
- Electrical, lighting and the exhaust fan
- Building the shower pan: slope, drain and curb
- Waterproofing the shower before tile
- The flood test: 24 hours of water before any tile
- Wall tile, niches and clean cuts
- Floor tile, grout and sealing
- Vanity, toilet and fixtures
- Shower glass, accessories and the final walkthrough
How long does a bathroom remodel take?
For a typical full bathroom with a tile shower, the work on site usually runs three to five weeks once the vanity and tile are on hand. The waterproofing cure and flood test alone take several days, and that time should never be skipped. Moving plumbing on a slab, repairing damage found behind the walls, and waiting for custom glass can add time.
Frequently asked questions
What should be chosen before a bathroom is demolished?
The shower valve, shower drain type, toilet, vanity and sink, and the location of niches, bench and grab bars. They decide the plumbing and framing.
In what order is a bathroom remodeled?
Demolition, repairs, plumbing and electrical, shower pan and waterproofing, flood test, tile, vanity and fixtures, then glass and the final walkthrough.
How long does a bathroom remodel take?
Usually three to five weeks of work on site for a full bathroom with a tile shower, once materials are on hand.
Can a bathroom be remodeled without moving the plumbing?
Yes, and it is usually faster and less expensive. Keeping the toilet and drains in place is a common way to control the budget.
What comes next
In Part 2 we protect the rest of the house and shut the bathroom down before demolition.
Planning a bathroom remodel in Wellington or nearby? See our bathroom remodeling page or schedule a site visit with Edgar at stronghandsflpro.com/contact or (754) 261-2153.