Tiled shower with curb and floor sloped to the drain

The shower is fully waterproofed and cured, as described in Part 9. Before any tile covers that work, we prove it holds water. The flood test is short to explain, takes a full day, and is one of the most valuable days of the whole remodel.

Why test before tile

Once tile is set, the membrane is hidden. A pinhole in a corner, a gap at the drain connection or a seam that did not bond would show up months later as a stain on the bedroom wall or a soft baseboard. At that point, the fix means taking the tile off. Testing before tile turns a possible future leak into a ten-minute repair today.

Step 1: Wait for the full cure

The test only means something if the membrane is fully cured. We follow the manufacturer’s cure time for the product, the temperature and the humidity. Testing a membrane that is still soft can damage it.

Step 2: Plug the drain

Step 3: Dam the entry

Step 4: Fill the shower

Water is added until it covers the highest point of the shower floor, usually about 1 to 2 inches at the high side, and up onto the base of the walls and the curb. That puts water on the floor, the corners, the drain connection and the lower wall seams at the same time.

Step 5: Mark and wait 24 hours

Step 6: Check

After 24 hours we look at three things:

  1. The water line. It should be at the same mark. A small drop from evaporation is possible in a hot, dry room, but a clear drop means a leak.
  2. Outside the shower. The walls on the other side of the shower, the floor around the curb, the room below if there is one, the baseboards in the next room.
  3. The drain. Under the drain connection, if accessible, and around the drain body.

If everything holds, the water is drained, the dam is removed, the plug comes out, and the membrane is left to dry before tile.

What happens if the test fails

It happens, and finding it now is the point of the test.

  1. Drain the shower and find the leak: usually a corner, the drain connection, a seam at the curb or a pipe penetration.
  2. Repair the spot with the same system, following the maker’s repair method, and let it cure.
  3. Test again for another 24 hours.

Tile does not go on until the shower passes.

Testing the rest of the bathroom

Frequently asked questions

What is a shower flood test?

The shower drain is plugged and the shower floor is filled with water over the waterproofing, then left for 24 hours to confirm nothing leaks before tile is installed.

How long does a flood test last?

Usually 24 hours, following the waterproofing maker’s instructions.

What if the flood test fails?

The leak is found, repaired with the same waterproofing system, cured and tested again. Tile waits until the shower passes.

Is a flood test done on curbless showers?

Yes, with a temporary dam at the entry to hold the water over the highest point of the floor.

What comes next

The shower is proven waterproof. In Part 11 the tile finally goes on the walls: layout, niches and clean cuts.

Planning a bathroom remodel in Parkland or nearby? See our bathroom remodeling page or schedule a site visit with Edgar at stronghandsflpro.com/contact or (754) 261-2153.