In Part 1 we measured the room and located every pipe, wire and duct before the design was drawn. Now the design is set, the materials are ordered and it is time to take the old kitchen out.
Most people picture demolition as a crew with sledgehammers and a dumpster in the driveway. On a kitchen remodel in a house where a family is still living, that picture is mostly wrong. The real work of this stage is everything that happens before the first cabinet comes off the wall, and the care taken while it does.
Step 1: Protect the path and the rooms that stay
The kitchen is usually in the middle of the house, so every board, every cabinet and every bag of debris has to travel through rooms you still use. Before any tool comes out, we protect the whole route from the kitchen to the door we will use for the job.
- Floors. Heavy floor protection board taped at the seams, from the kitchen to the exit door. Tile and wood floors in the rest of the house are the easiest thing to damage and the hardest to repair invisibly.
- Corners and door frames. Corner guards on the walls along the path, and padding on door jambs where cabinets and appliances will be carried out.
- Furniture nearby. Moved out of the way or covered with plastic and taped closed, not just draped.
- Entry door. One door becomes the work door, so the front entry stays clean for the family.
Step 2: Build a dust wall
Drywall and plaster dust is fine enough to travel through the whole house and settle on every surface. We close the kitchen off with a floor to ceiling plastic barrier on spring poles, with a zipper door to get in and out. Open doorways to other rooms are sealed the same way.
A small detail that makes a big difference: a fan in a kitchen window blowing out. It keeps the air pressure in the work area slightly lower than the rest of the house, so when the zipper opens, air flows into the kitchen instead of out of it, and the dust goes with it.
Step 3: Take care of the AC
In South Florida the AC runs most of the year, and it is the fastest way to spread dust through a house. Supply registers and the return grille inside the work area get covered and taped. If the return for the house is near the kitchen, we plan with the homeowner to run the system as little as possible during the dustiest days and change the filter when demolition ends. A clogged filter after demolition is one of those things nobody thinks about until the system starts struggling.
Step 4: Shut off and make safe every utility
Before anything is unscrewed, the kitchen has to be dead, dry and safe.
- Electrical. Kitchen circuits are turned off at the panel and labeled so nobody turns them back on. Then every outlet and fixture is checked with a tester. Panel labels in older homes are often wrong, so we never trust a breaker label alone.
- Water. Shutoff valves under the sink and at the dishwasher are closed. If those valves are old and seized, which is common, water to the house is shut at the main and the lines are capped properly before the cabinet comes out.
- Gas. If there is a gas range, the gas is shut off and the line is capped by a qualified tradesperson before the range moves an inch.
- Refrigerator ice maker line. Easy to forget, and a small copper line behind the fridge can leak for hours before anyone notices.
Step 5: Check what the old materials are made of
In older homes, some flooring, mastic adhesive, textured ceilings and joint compound can contain asbestos. When the age of the house and the materials raise that question, we test before we disturb them. If a test comes back positive, that material is handled by a specialist, not by a demolition crew. It is one extra step that protects your family and our people.
Step 6: Demolition, in order
Demolition goes in reverse order of how the kitchen was built, so each piece comes out without damaging the next.
- Appliances out first, disconnected and carried out on dollies, or set aside if they are being reused.
- Countertops next. Stone is cut or lifted off in sections. Laminate comes off after the screws under it are removed.
- Upper cabinets, then base cabinets. They are unscrewed, not ripped off. That protects the walls we plan to keep and leaves cabinets in good shape if the owner wants to donate or reuse them.
- Backsplash and drywall, only where the scope calls for it.
- Flooring last, if it is part of the job.
We keep the tear out to what the design needs. Every extra square foot of wall that comes down is a square foot that has to be rebuilt, finished and painted. Careful demolition saves work in every stage that follows.
Step 7: Look at what demolition reveals
When the cabinets and drywall come off, the house tells you its history. This is where we slow down and look before moving on. Things we commonly find in kitchens in Fort Lauderdale, Pompano Beach and the rest of Broward and Palm Beach:
- Water damage under the old sink or behind the dishwasher, sometimes years old.
- Termite damage in wood framing or in the base of door frames.
- Wiring that was extended over the years with splices hidden inside walls.
- Furring strips on concrete block walls that are loose or rotted at the bottom.
- Old pipe repairs that were never done right.
Each item gets photographed and explained to the homeowner the same day. Some are minor and get fixed as part of the next stage. Others change the plan a little. Either way, you see it with your own eyes and decide with full information.
Step 8: Clean, every day
Debris leaves the house daily, not at the end of the week. The work area is swept and vacuumed at the end of every shift, and the protection along the path is checked and retaped where needed. A job site that is organized at 5 PM is a job site where tools do not get lost and nothing gets stepped on.
Edgar is on site for every stage, and demolition is one where it matters. Deciding what comes out, what stays and what we just found behind the wall needs someone with experience standing in the room.
What comes next
With the old kitchen out and the room open, we can see every stud, pipe and wire. Part 3 covers the rough electrical and plumbing, and the visual inspection of everything that will soon be hidden behind new walls.