New drywall finished and upper cabinets being installed during a kitchen remodel

In Part 3 we ran the new wires, pipes and ducts and checked every one of them with the walls still open. Now the walls get built back.

Closing a wall sounds simple: hang drywall, tape, paint. In a kitchen, the walls do more work than anywhere else in the house. They carry hundreds of pounds of upper cabinets, plates and glassware. They have to be flat enough for a long run of cabinets and a tile backsplash with straight grout lines. And part of them lives next to a sink. This stage is where those details get built in.

Step 1: Straighten the studs

Wood studs are never perfectly straight. Some bow in, some bow out, some twist. On a bedroom wall, nobody notices. Behind a 10 foot run of upper cabinets, a stud that bows out a quarter inch can push one cabinet forward and leave a visible gap behind the one next to it.

We run a long straightedge or a string line across the studs where the cabinets will hang. Studs that stick out get planed down. Studs that are set back get shimmed or sistered with a straight board alongside. It takes an hour or two on a typical kitchen and saves a lot of fighting during cabinet installation.

Step 2: Blocking for the upper cabinets

This is the detail we most like to point out to homeowners, because almost nobody knows it exists.

Upper cabinets are screwed to the wall through a rail at the back. If those screws only hit studs, the cabinet hangs from whatever studs happen to fall within its width, sometimes just one. Before the drywall goes up, we install horizontal wood blocking between the studs across the whole height where the upper cabinet rails will land. With solid wood behind the drywall along the full length of the wall, every cabinet can be fastened exactly where it needs to be, at both ends, no matter where the studs are.

Other places that get blocking

Every piece of blocking is photographed with a tape measure in the shot and marked on the drawings. Later, the installer knows exactly where the solid wood is.

Step 3: Exterior walls of concrete block

Many homes in Coral Springs, Parkland and across South Florida have exterior walls of concrete block with wood furring strips and drywall on the inside. When a kitchen sits on one of those walls, the cabinets are not hanging on wood studs at all.

Two things matter here. First, the furring strips have to be in good condition and firmly attached, because old strips near the floor are often loose or water damaged. Second, the upper cabinets need a solid fastening plan. Either the cabinets are anchored through to the block with masonry screws at planned points, or extra furring is added at the cabinet rail height so there is continuous wood to fasten into. Which one we use depends on the wall, but it is decided now, before the drywall covers it.

Step 4: Insulation

Exterior walls get insulation before they are closed. It keeps the kitchen cooler and the AC running less. Interior walls next to a pantry or a laundry room can get sound insulation if the owner wants a quieter kitchen. It costs little at this stage and is very hard to add later.

Step 5: The right drywall in the right place

Not every sheet of drywall in a kitchen is the same. Around the sink and behind the dishwasher, where water and humidity are likely, we use moisture and mold resistant board. In South Florida, with humidity high most of the year, that choice matters more than it does up north.

Sheets are hung horizontally where possible, so there are fewer joints to finish. Screws go in at the right spacing and depth: just below the surface without tearing the paper. A screw that tears the face paper has almost no holding power and pops through the paint a year later.

Every outlet box from Part 3 is cut out cleanly with a tight fit. Gaps around boxes are the most common sign of rushed drywall, and they are easy to see once the cover plates go on.

Step 6: Taping and finishing

Joints get tape and three coats of compound, each sanded smooth before the next one. The finish level depends on what goes on the wall.

Before priming, we check flatness again with a long straightedge, especially along the backsplash and on any wall where tall cabinets will sit.

Step 7: Prime and mark

The walls get a coat of primer, which seals the compound and shows any imperfection that needs one more touch. Then the layout lines go back on the wall: cabinet heights, the center of the sink and the range, and the locations of all the blocking. Those lines guide the next stages, so nobody has to guess where to drive a screw.

Edgar checks the closed walls against the plan before the room moves on. A wall that is not right at this point is still easy to fix. A wall that is not right after the cabinets are hung is not.

What comes next

With the walls closed and flat, the last step before cabinets is the floor. Part 5 covers how we check and level a slab, why the floor has to be flat before the first base cabinet goes in, and how flooring and cabinets are coordinated.

Planning a kitchen remodel in Coral Springs or nearby in Broward County? See our kitchen remodeling work or call Edgar at (754) 261-2153.