Upper cabinets installed above base cabinets during a kitchen remodel

In Part 8 the base cabinets and the island went in: level, joined and anchored. Today the upper cabinets go up, and then the finishing pieces that make a set of boxes look like built-in furniture.

Upper cabinets have a different job from base cabinets. Nothing holds them up from below. A loaded wall cabinet full of plates and glassware can easily carry well over a hundred pounds, all of it hanging on screws. Hanging them right is a safety job first and a looks job second.

Step 1: Set the height

A level line is drawn across every wall at the bottom of the uppers. Just like the bases, every upper is set to this line.

Step 2: A ledger board to hold the weight while we work

We screw a straight, temporary ledger board to the wall with its top edge on the level line. The upper cabinets rest on it while they are leveled and screwed. It keeps the boxes in line and keeps nobody holding a cabinet over their head while someone else drives screws. The ledger comes off once the cabinets are secured, and the screw holes are hidden behind the backsplash.

Step 3: Screw into framing, never only into drywall

On concrete block exterior walls, which are common in South Florida homes, the cabinets are fastened to the wood furring or blocking added in Part 4, or with anchors rated for masonry. A drywall anchor alone is never enough for a kitchen cabinet.

Step 4: Start in the corner and work out

Like the bases, the uppers start at the corner. The corner cabinet is set on the ledger, leveled, plumbed and screwed. Each next cabinet is clamped to its neighbor so the face frames are flush at the front and bottom, joined with connector screws, and only then screwed to the wall.

We check with a long level along the bottoms and a straightedge across the faces every few cabinets. On an upper run, a small step between two cabinets is easy to see when you stand at the counter.

Step 5: Fillers and scribes

Walls are not perfectly straight or square. Fillers are the strips that close the space between a cabinet and a wall, and they also give doors and drawers room to open.

Step 6: End panels and appliance panels

Any cabinet side that will be seen, at the end of a run, next to the refrigerator or on the island, gets a finished panel. Factory cabinet sides are often not meant to be on display.

Step 7: Crown molding and light rail

Step 8: Doors, drawers and hardware

Step 9: Final check before the countertop template

Frequently asked questions

How high should upper cabinets be above the counter?

Usually 18 inches above a standard 36 inch counter, which puts the bottom of the uppers 54 inches from the floor. The range hood height follows the hood manufacturer’s requirements.

What holds upper cabinets on the wall?

Cabinet screws through the solid hanging rails into studs or blocking at the top and bottom of each cabinet. Never drywall anchors alone.

What are cabinet fillers for?

They close the space between a cabinet and a wall and give doors and drawers room to open without hitting the wall or an appliance.

Why are some cabinets finished with panels?

Any side of a cabinet that will be seen, like the end of a run or the island, gets a finished panel so it looks like furniture instead of a raw cabinet side.

When are knobs and pulls installed?

After the doors and drawers are adjusted. A drilling template keeps every pull in exactly the same position.

What comes next

The cabinets are finished. In Part 10 the countertop shop comes to template the stone on the real cabinets, and we explain what happens at the fabricator before installation day.