Open kitchen walls during rough plumbing and electrical, with new water lines in place

In Part 2 we protected the house and took the old kitchen out. The room is now open: studs, block, slab and ceiling joists, with old pipes and wires sticking out where the previous kitchen used them.

This stage is called the rough in. It is the part of the remodel you will never see again once the walls are closed, and it decides how well the kitchen works for the next 20 or 30 years. Every outlet, every light, every water line and every drain in the new design gets placed now, exactly where the cabinet drawings say it should be.

Start from the cabinet drawings, not from the old kitchen

The first step is marking the layout directly on the walls and floor. Using the cabinet drawings and the appliance specification sheets, we draw on the studs where each cabinet starts and ends, the countertop height, the sink center, the range center and the hood. Then every rough in location is measured from those marks.

It sounds obvious, but this is where many kitchens go wrong. An outlet roughed in 2 inches off can end up behind a cabinet side panel. A water line 3 inches too far left can hit the dishwasher. Marking the real layout on the wall first prevents all of that.

Rough electrical

Circuits

A remodeled kitchen almost always needs more power than the old one. A typical layout includes:

Before adding circuits, we confirm the panel has the room and the capacity for them. That was measured back in Part 1, so there are no surprises here.

Outlets along the counter

Countertop outlets are spaced so that no point along the counter is more than 2 feet from an outlet, and every counter space 12 inches or wider gets one. They are protected by GFCI. Islands and peninsulas need their own outlets too. We set the boxes at a height that clears the backsplash material, so a tile row is not cut in half around every cover plate.

Boxes you would never think about

Rough plumbing

Water supply

Supply lines for the sink, the dishwasher and the refrigerator ice maker are run to their final positions. Each one gets its own shutoff valve in an accessible spot. The sink supply lines come out of the wall at a height that leaves room for the drawers or the disposal below.

Before anything is covered, the new water lines are pressure tested. The system is filled and held under pressure for a set time while we watch the gauge. If the needle drops, there is a leak somewhere, and it gets found now, not after the cabinets are installed.

Drain and vent

Drains need slope, usually a quarter inch per foot, to carry water and food waste properly. The drain height at the wall has to work with the sink depth and the disposal, or the sink will drain slowly forever.

Most homes in Delray Beach, Boynton Beach and the rest of Palm Beach County are built on a slab. When a sink moves to a new island, the slab is cut, a trench is dug and a new drain runs underground to the existing line. Venting an island sink takes its own plan, because there is no wall above it to run a vent pipe through. That plan is set before the trench is closed.

One Florida detail: homes here usually had a termite treatment applied to the soil under the slab when they were built. When a trench breaks through the slab, that soil gets disturbed, and treating the trench area before it is backfilled is good practice.

Gas

If the design includes a gas range or cooktop, the gas line is run to the location on the specification sheet, with a shutoff valve where it can be reached after the range is in place. New gas lines are pressure tested as well, and all gas work is done by a qualified gas tradesperson.

Ventilation

The hood duct is planned now, with the shortest run to the outside and the fewest turns possible. Every elbow reduces how much smoke and grease the hood can actually move. The duct is sealed at every joint, and the exterior cap gets a damper so outside air and insects do not come in.

The walk through before the walls close

This is one of the most important hours of the whole remodel, and it takes very little time. Before any insulation or drywall goes up, Edgar walks the open room with the drawings in hand and checks every rough in against the plan.

Photograph every wall

The last step of this stage costs nothing and is worth a lot later: we photograph every open wall with a tape measure in the shot, showing exactly where each wire and pipe runs. Years from now, when someone wants to hang a heavy shelf or add an outlet, those photos show what is behind the drywall without cutting a single hole. The homeowner gets a copy.

What comes next

With the rough in done and checked, the walls can be built back. Part 4 covers framing corrections, the wood blocking that holds up heavy upper cabinets, and drywall done the way a kitchen needs it.