In Part 4 we straightened the studs, added blocking for the cabinets and closed the walls. Before the first base cabinet comes into the room, there is one more surface to get right: the floor.

The floor is the reference for everything above it. Base cabinets sit on it, the countertop sits on the cabinets, the backsplash starts at the countertop and the upper cabinets line up with all of it. If the floor is out of level and nobody deals with it, the error travels all the way up the wall.

Step 1: Map the floor again

Back in Part 1 we shot the floor with a laser before anything was designed. Now, with the old cabinets and flooring gone, we can see the bare slab and map it properly. The laser goes in the middle of the room and we take readings on a grid every couple of feet, writing each number on the floor in marker. In twenty minutes the slab has a topographic map drawn right on it: the high spots, the low spots and how the floor drops toward a door or a wall.

Most homes in West Palm Beach, Wellington, Lake Worth and the rest of South Florida sit on a concrete slab. Slabs are poured by hand, and a difference of half an inch or more across a kitchen is normal. Old tile removal also leaves ridges of thinset and adhesive that have to come off before any reading means anything.

Step 2: Two numbers, two different jobs

There are two separate questions here, and people often mix them up.

A floor can be flat but slightly out of level, like a smooth ramp. It can also be level overall with a dip in the middle. Each problem has its own fix.

Step 3: Flat enough for the flooring you picked

The flooring material decides how flat the slab has to be. Large format tile is the most demanding. The industry standard for tile with any side 15 inches or longer allows no more than an eighth of an inch of variation in 10 feet, and no more than a sixteenth of an inch over 2 feet. Large tiles do not bend to follow a dip. If the slab is not flat, the tile edges sit at different heights, which is called lippage, and you feel it with your bare feet every morning.

Luxury vinyl plank looks forgiving, but it has its own limits. Over a dip it flexes every time someone steps on it, and the locking joints can separate over time. Wood floors need a flat base too.

Step 4: Grind the highs, fill the lows

The primer step is the one that gets skipped most often. Without it, a dry slab pulls water out of the leveling compound too fast, and it can crack or lose its bond. One coat of primer protects the whole pour.

Step 5: Test for moisture

Concrete slabs hold moisture, and in South Florida the ground under them is never really dry. Water vapor moving up through a slab can ruin a wood floor, loosen vinyl planks and cause adhesive to fail. Before any moisture sensitive flooring goes down, we test the slab and compare the result to what the flooring manufacturer requires. If the number is too high, the floor gets a moisture barrier or a different installation method. Skipping that test is how a new floor starts to cup a few months later.

Step 6: Decide the order of floor and cabinets

There are two ways to do it, and both work when they are planned.

Flooring first, under the cabinets

The new floor runs wall to wall, and the cabinets sit on top of it. This gives the most flexibility if the layout ever changes, and it makes appliance spaces easy, because the floor is already under the dishwasher and the fridge.

Cabinets first, flooring up to them

The cabinets go on the slab and the flooring is installed up to the toe kick. This uses less material and is common with floating floors that need room to move. The catch is height. If the new floor goes in after the cabinets, it raises the floor in front of the dishwasher. Most dishwashers need a set opening height, and a thick tile plus its setting bed can take enough of it that the dishwasher no longer slides in or out. The fix is simple: put flooring or a matching spacer under the dishwasher and fridge spaces before the cabinets go in. It is just easy to forget.

Step 7: Set the cabinet reference line

Once the floor is ready, we find the highest point of the floor where the base cabinets will sit. That point becomes the reference. A level line is drawn on the wall at the top of the base cabinets, measured up from that high point, all the way around the kitchen. Every base cabinet is set to that line and shimmed up where the floor is lower.

Starting from the high point means the countertop height is never lower than the design anywhere, and the dishwasher opening and the range height come out right. Starting from a low point means one cabinet will have to be cut down later, which never looks good.

Edgar checks the floor map, the leveling work and the reference line before the cabinets are delivered. It is the last chance to fix the base of the kitchen easily.

What comes next

With straight walls, solid blocking and a flat, level floor, the room is ready for the new floor. In Part 6 we lay out and set the tile, in Part 7 we grout and seal it, and in Part 8 the first base cabinet goes in.

Planning a kitchen remodel in West Palm Beach or anywhere in Palm Beach and Broward Counties? See our kitchen remodeling work or call Edgar at (754) 261-2153.