In Part 5 we roughed in the supply lines and the valve inside the walls. When the layout stays the same, the drains stay where they are. When it changes, for example a toilet moving to another wall, a tub becoming a walk-in shower with a drain in a new place, or a second sink, the drains have to move. In most South Florida homes, that means cutting into the concrete slab.
This part covers how that is done. It is one of the stages that most changes the cost and the schedule of a bathroom, which is why it is decided in Part 1, before demolition.
Step 1: Find the existing lines
Before any cut, we need to know where the drain lines run under the slab and where they connect.
- Trace from the fixtures. The old toilet flange, tub drain and vanity drain show where the branches start.
- Follow the main. We confirm which direction the drains run to the main line.
- Check for other lines. Water lines and sometimes electrical conduit can also run in or under the slab. We mark everything known before cutting.
- Camera, when needed. On older homes, a sewer camera through the drain shows the pipe material, the condition and the direction, and catches problems like old cast iron that is cracked or scaled inside.
Step 2: Plan the new route and the slope
A drain does not work by pressure. It works by gravity. Every drain line needs a constant downward slope toward the main, usually 1/4 inch per foot for bathroom drains. That rule decides how far a drain can move:
- Moving the toilet a short distance along the same line is usually simple.
- Moving it farther means a longer trench, and the new line must still connect with enough fall. If the existing connection point is shallow, the distance is limited.
- Vents. A drain that moves too far from its vent may need a new vent connection.
We draw the new route on the slab with paint, including the trench width, before any saw touches the concrete.
Step 3: Saw cut and remove the concrete
- Saw cut. We cut the outline of the trench with a concrete saw, using water to control dust, with the room sealed as in Part 2.
- Break out. The concrete inside the cut is broken with a rotary or demolition hammer and removed in pieces.
- Dig. The soil under the slab is dug out to the depth needed for the slope, carefully around existing pipes.
- Keep the edges clean. Straight saw cuts make a much stronger patch than a broken, ragged edge.
Step 4: Install the new drain
- Pipe and fittings. New drain lines in PVC are cut and joined with the right fittings: long sweeps for direction changes, never sharp turns that slow the flow.
- Slope checked with a level on every section before backfill.
- Toilet flange. Set at the exact rough-in distance from the finished wall, usually 12 inches to the center, and at the right height for the finished floor. A flange that sits too low or too high is a common cause of leaking wax rings.
- Shower drain. Placed for the shower pan design: centered for a center drain, or along the wall or entry for a linear drain, as we cover in Part 8.
- Connection to the existing line with the right transition fittings, especially when connecting new PVC to old cast iron.
Step 5: Test before burying
The new drains are filled with water up to the floor level and left for a set period. The water level must not drop. Every joint is checked. Only a line that holds is buried. When the work requires an inspection, it happens now, with the trench open.
Step 6: Backfill and patch the slab
- Backfill with clean fill compacted in layers around and over the pipe, so the patch does not settle later.
- Vapor barrier over the fill, matching the existing slab, so ground moisture does not come up through the patch.
- Concrete. The trench is filled with concrete to the level of the surrounding slab, finished flat. A cold joint between old and new concrete is expected and is handled by the crack isolation membrane under the tile.
- Cure. The patch cures before tile or waterproofing goes on it, following the concrete’s cure time.
Frequently asked questions
Can a toilet be moved on a concrete slab?
Yes. The slab is cut, a new drain is installed with the right slope, tested and the concrete is patched. It adds time and cost compared with keeping the toilet in place.
How far can a drain be moved?
It depends on the depth of the existing connection and the slope needed, usually 1/4 inch per foot. The farther it moves, the deeper the trench must be at the start.
Is cutting the slab safe for the house?
A trench for plumbing in a residential slab is a routine repair when it is cut cleanly, backfilled, compacted and patched with a vapor barrier.
How long does moving a drain take?
Usually two to four days including cutting, plumbing, testing and patching, plus the cure time of the concrete patch.
What comes next
In Part 7 we cover the electrical work in the bathroom: GFCI protection, lighting at the vanity and the exhaust fan that keeps a South Florida bathroom dry.
Planning a bathroom remodel in Delray Beach or nearby? See our bathroom remodeling page or schedule a site visit with Edgar at stronghandsflpro.com/contact or (754) 261-2153.